Client Problem

Our Solution

More Case Studies

“South Lambeth Road went from a 7-day cycle per floor to 5-days, based solely on Converge. The client not only dropped penalties for late delivery - they asked us to tender for another project!"

Superstructure
S. Lambeth Rd.

"For post-tensioning, the 1st and 2nd tensions can be done within 40 hours (morning after for initial and morning after that for final) of finishing the pour. Striking formwork from the slab can begin within 48 hours. This would save half a day per floor when compared to a cube testing regime. The customer service provided by the guys is second to none. I would definitely use the Converge system on future projects and recommend it to fellow engineering professionals."

Superstructure
Principal Place
Infrastructure
Blyth Offshore